Total Savings
£230,687.00
Avg Savings %
44.6%
Procurements
8
Would-Have-Spent
£624,591.00

Savings Breakdown — High vs Low

Procurement School Highest Quote Lowest Quote Accepted Quote Savings Savings % Completed
Smart thermostat installation across campus Westgate Primary £86,473.00 £22,387.00 £22,387.00 £14,818.00 39.8% 19 Feb 2026
LED lighting retrofit - All corridors St. Mary's High School £94,299.00 £35,821.00 £35,821.00 £23,069.00 39.2% 18 Feb 2026
Boiler replacement - Gas to heat … Greenfield Secondary £92,846.00 £22,947.00 £22,947.00 £69,899.00 75.3% 18 Feb 2026
Ventilation ductwork cleaning and repair Westgate Primary £83,809.00 £71,225.00 £71,225.00 £12,584.00 15.0% 18 Feb 2026
Emergency roof membrane repair - Building … Riverside Primary School £55,362.00 £33,150.00 £33,150.00 £20,502.00 38.2% 17 Feb 2026
HVAC compressor replacement - Main Hall Riverside Primary School £60,985.00 £23,457.00 £23,457.00 £37,528.00 61.5% 16 Feb 2026
Fire alarm system upgrade Greenfield Secondary £58,315.00 £9,221.00 £9,221.00 £49,094.00 84.2% 16 Feb 2026
Fire alarm system upgrade Hillcrest Grammar School £92,502.00 £83,763.00 £83,763.00 £3,193.00 3.7% 16 Feb 2026
Totals: £230687.00 44.6%

Savings by School

School Procurements Total Savings Avg Savings %
Greenfield Secondary 2 £118,993.00 79.7%
Riverside Primary School 2 £58,030.00 49.9%
Westgate Primary 2 £27,402.00 27.4%
St. Mary's High School 1 £23,069.00 39.2%
Hillcrest Grammar School 1 £3,193.00 3.7%